Work set to begin on crosswalk for Baxter employees on Albert St.
Posted September 28, 2026
Installation of a pedestrian activated crosswalk at the intersection of Albert and Centre Street in Alliston begins this week and take about a month to complete.
The project is more than three years in the works, requested then by Baxter Corporation to help its employees access its parking lot located across the street. Baxter is funding the work, which in 2023 was estimated to cost $95,600.
Installation includes:
-
New concrete sidewalks
-
A marked pedestrian crossover
-
Pedestrian signals, push buttons and flashing beacons
-
New signage
-
Upgraded street lighting
-
Other related infrastructure improvements
Construction is expected to be completed by November 6, 2026, weather permitting.
Traffic will continue to flow through the area during construction with temporary lane reductions.
.